Pink and Magenta Lines to boost Metro's carriage capacity

New Delhi: Delhi Metro is all set to facilitate more than 2 lakh additional commuters on its Phase-3, which is about to be operational by March 2018. Besides the entirely new Pink and Mangenta Lines, the DMRC will be adding 186 new coaches to the existing lines.
Meanwhile, these two lines will be able to ferry 1,51,200 passengers. Calculated at 300 passengers per coach as cited by the transporter, the DMRC will be able to accommodate an additional 55,800 commuters on its five existing lines.
And the commissioning of Pink Line (Majlis park-Shiv Vihar) and Magenta Line (Janakpuri West-Botanical Garden), which will be done in phases from December, will add 504 more coaches to the network by March next year, when they will be fully operational.
A DMRC official confirmed that it is "safe to say" that the commuter capacity will increase by a little over 200,000 a day, given the capacity of a coach and the increase in their number.
"It is safe to say this... but the accurate number is hard to calculate. Since we do not have the relative ridership data, or any projection in its increase which may occur during this period," Tomojit Bhattacharjee, Manager, Corporate Communication, DMRC, said.
Currently, 227 trains with 1,468 coaches ply on the Delhi Metro's five lines -- Red, Yellow, Blue, Green and Violet -- with the number of coaches varying from four to six to eight.
By the end of Phase-3, the official said, the number of trains on these lines is scheduled to increase to 244 and the number of coaches to 1,654.
Started in 2002 with a fleet of only four-coach trains, the DMRC has periodically resorted to adding coaches to accommodate more and more passengers.
Following the same tested method, the DMRC has decided to increase the number of coaches and trains on three of its lines -- Red Line, Yellow Line, and Blue Line.
Supporting almost one-third of the network's daily traffic of 2.7-2.9 million, the Yellow Line (Huda City Centre-Jahangirpuri) is slated to see a major boost in terms of number of trains and coaches.
Currently at 436 coaches, by the end of Phase-3, the stretch will have 488 coaches, with 10 out of its 22 six-coach trains having been converted into eight-coach ones.
Eventually, the line will have a total of 52 maximum-coach trains (including four new eight-coach trains), increased from the present 38.
Likewise, the Blue Line (Dwarka Sector-21-Vaishali/Noida City Centre) will also see a moderate increase, with the number of coaches slated to be increased from 538 to 574.
A major change will be seen on the oldest line in the network, where the entire fleet of four-coach trains will be converted into six-coach ones, increasing the number of coaches from 136 to 234.
The Red Line (Rithala-Dilshad Garden), which at present has 19 four-coach trains, will boast of 39 six-coach trains by the end of Phase-3, with no four-coach trains remaining in service at all. The line does not have any eight-coach trains.
At present, the daily ridership is 900,000 on the Yellow and Blue Lines and 350,000 on the Red Line. The Phase-3 project also includes extension of the Green Line (Mundka-Kirti Nagar/Inderlok) from Mundka to Bahadurgarh and that of Violet Line (Kashmere Gate- Escorts Mujesar) to Ballabhgarh in Haryana.