Coal India may miss output target by about 12 MT for current fiscal

Battling on various fronts to boost production, the world’s largest miner Coal India Ltd may miss the target by about 12 million tonnes for the current fiscal as it struggles to achieve at least 470 MT.

The state-owned firm had fixed a target of 482 MT for 2013-14 financial year ending 31 March.

‘As per estimates, we are likely to achieve an output of 470 MT for the fiscal as a number of factors have resulted in less output. We may miss the target by more than 10 MT,’ Coal India chairman and managing director S Narsing Rao said.

Rao attributed the projected production loss to a number of factors, including delays in securing clearances to CIL projects, cyclone Phailin and problems in evacuation among others.

‘Production was hit by 5 MT due to cyclone Phailin. Besides, many of our projects are delayed due to regulatory hurdles including forest clearances. There are law and order issues also, and in July and August the demand was less from consumers and we cannot store coal at open case mines,’ Rao said.

The PSU’s coal executives strike on 13 March, too, caused an output loss to the tune of 4 lakh tonnes.
Rao also cited infrastructure problems saying the ‘there is virtually no significant progress’ in the critical rail links due to which the company was unable to tap the potential for supplying 300 MT.

‘Under the circumstances, we are in a position to increase our annual growth to only 30 MT for the next few years,’ he said. If three rail links are fast-tracked, the company will ensure 300 MT additional supply to consumers. 

Three rail corridors are: Tori-Shivpuri-Kathotia in North Karanpura, Jharkhand; Bhupdeopur-Korichhaapar to Mand Raigadh mines in Chhattisgarh; and Barpali-Jharsuguda in IB Valley, Odisha, which are under different phases of development.