‘Expedite JNNURM housing project’
BY PTI5 Sept 2014 4:08 AM IST
PTI5 Sept 2014 4:08 AM IST
Expressing concern over substantial shortfall in meeting the target for construction of houses under JNNURM in the capital, urban development and housing minister Venkaiah Naidu on Wednesday asked Delhi administration to expedite the project.
In a meeting to review the status of construction of houses under JNNURM, it was reported that as against the sanctioned 64,184 dwelling units in Delhi, construction of only 22,924 units has been completed, out of which only 585 have been occupied so far.
Naidu spoke to Lieutenant Governor Najeeb Jung and Delhi chief secretary DM Spolia and discussed issues relating to shortfall in JNNURM housing project, a senior urban development ministry official said.
Senior officials of the urban development ministry and DDA Vice-Chairman Balwinder Kumar attended the meeting. Naidu expressed concern over the substantial shortfall in respect of physical
targets in respect of construction of houses under JNNURM and asked both of them to take necessary measures to ensure allotment and occupation of the 22,300 houses constructed besides ensuring
completion of the remaining houses for which the ministry has already released committed share of central assistance.
In a meeting to review the status of construction of houses under JNNURM, it was reported that as against the sanctioned 64,184 dwelling units in Delhi, construction of only 22,924 units has been completed, out of which only 585 have been occupied so far.
Naidu spoke to Lieutenant Governor Najeeb Jung and Delhi chief secretary DM Spolia and discussed issues relating to shortfall in JNNURM housing project, a senior urban development ministry official said.
Senior officials of the urban development ministry and DDA Vice-Chairman Balwinder Kumar attended the meeting. Naidu expressed concern over the substantial shortfall in respect of physical
targets in respect of construction of houses under JNNURM and asked both of them to take necessary measures to ensure allotment and occupation of the 22,300 houses constructed besides ensuring
completion of the remaining houses for which the ministry has already released committed share of central assistance.