331 infra projects see cost overrun of Rs. 1.72 lakh crore
BY M Post Bureau23 Oct 2017 11:36 PM IST
M Post Bureau23 Oct 2017 11:36 PM IST
New Delhi: As many as 331 infrastructure projects, each worth Rs 150 crore or above, have seen a cost overrun of Rs 1.72 lakh crore because of various reasons including delays, according to a government report.
Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 and above.
The total original cost of implementing 1,257 projects was Rs 15,76,903.56 crore, and their anticipated completion cost is likely to be Rs 17,49,274.62 crore, cost overrun of Rs 1,72,371.06 crore (10.93 percent of the original), the ministry's flash report for July this year has stated.
The expenditure incurred on these projects till July is Rs 6,80,016.96 crore, which is 38.87 percent of the total anticipated cost.
The 1,257 projects in question include 331 that reported cost overrun and 274-time escalation.
"Out of a total of 1,257 projects, two projects have reported completion, and ten new projects have been initiated on the monitor of this ministry during the current month (July).
Of these, 11 projects are ahead of schedule, 304 are on track and 274 are delayed, 331 projects are showing cost overrun and 92 projects are showing both time and cost overrun concerning original implementation schedules."
However, the report said that the number of delayed projects decreases to 215 if the delay is calculated with reference to latest revised schedules of completion.
The report also highlights that for 668 projects, the original/anticipated commissioning dates were not reported by the authorities concerned.
Next Story



