Bhel finishes historic grid-linking power sub-station in Karnataka
BY PTI7 Jan 2014 7:27 AM IST
PTI7 Jan 2014 7:27 AM IST
'Bhel has completed the construction of a sub-station at Raichur in Karnataka, the southern end of the Raichur-Solapur transmission link of PowerGrid,' the company said in a statement on Monday.
The government said on 1 January that the southern grid had been linked with the national grid following the commissioning of the Raichur-Solapur transmission line. The line had been commissioned five months ahead of the 31 May, 2014, deadline at a cost of about Rs 815 crore.
Bhel's work on the project included design, engineering, manufacturing, supply, erection, testing and commissioning of the substation.
The project will allow electricity to be carried to the southern region from other parts of the country during peak demand as well as transfer surplus power from the south during off-peak hours, it said.
Bhel is currently associated in the execution of an Ultra High-Voltage Multi-terminal DC (direct current) transmission link between the northeast and Agra, it added.
The government said on 1 January that the southern grid had been linked with the national grid following the commissioning of the Raichur-Solapur transmission line. The line had been commissioned five months ahead of the 31 May, 2014, deadline at a cost of about Rs 815 crore.
Bhel's work on the project included design, engineering, manufacturing, supply, erection, testing and commissioning of the substation.
The project will allow electricity to be carried to the southern region from other parts of the country during peak demand as well as transfer surplus power from the south during off-peak hours, it said.
Bhel is currently associated in the execution of an Ultra High-Voltage Multi-terminal DC (direct current) transmission link between the northeast and Agra, it added.
Next Story