Arunachal highway project facing roadblocks : Minister
BY Agencies10 March 2015 12:05 AM GMT
Agencies10 March 2015 12:05 AM GMT
The delay in execution of the ambitious Trans Arunachal Highway (TAH) project is mainly because of the compensation issue with the affected people and delay in final forest clearance by the Union ministry of Environment and Forest, Arunachal Pradesh PWD Minister Gojen Gadi informed the assembly on Monday. Congress member Pani Taram during Question Hour, Gadi expressed concern over the quantum of compensation claimed by the affected people.Â