Work resumes to complete Bhangar power sub-station

Update: 2018-08-14 17:50 GMT

Kolkata: The work to complete setting up of the Bhangar power sub-station has resumed on Tuesday.

It may be mentioned that the decision of starting the work to complete construction of the sub-station was taken up after the "final minutes" was signed on Saturday.

The "final minutes" was signed by representatives of the Jomi, Jibika, Poribesh O Bastutantra Rakshya Committee, Power Grid Corporation of India, West Bengal State Electricity Distribution Company Limited, top brass of the district police and the district magistrate of South 24-Parganas. A compensation package of Rs 12 crore for further development of the area was also announced.

Senior officials went to the site of the power sub-station and an assessment has been done to ensure that the remaining work gets completed as early as possible. Officials of the Power Grid Corporation of India also went to the site and carried out their necessary work.