Sterlite Power Grid Ventures has commissioned its Jabalpur Transmission project, which has been set up at an estimated cost of about Rs 1,500 crore. “Sterlite Power Grid Ventures (Sterlite Grid), a subsidiary of Pune-based Sterlite Technologies, announces <g data-gr-id="10">commissioning</g> of its Jabalpur transmission Project,” the company said in a press release.
Sterlite Grid charged the 379 km-long 765-kv double circuit Dharamjaygarh-Jabalpur transmission line, the longest 765-kv line in the country, on September 12. Earlier in June 2015, Sterlite Grid successfully commissioned the stretch of 236-km Jabalpur-Bina transmission line. After commissioning both the constituents of Jabalpur Transmission Company (JTCL), Sterlite Grid has become the first private developer to complete 765 <g data-gr-id="9">kv</g> double circuit transmission system, it said.